WHEN DID DEADLINES STOP BEING DEADLINES IN BENUE?

Golden Soya Oil has missed Dr. Raymond Asemakaha's November 9 market deadline, with BIPC shifting expectations to December 5 without adequately explaining the delay. But Taraku Mills is only one example of a growing accountability concern under Governor Alia. From the ₦62 billion Gboko road project to the Awajir–Oju road and Makurdi underpasses, Benue people deserve explanations for missed project deadlines. Government cannot keep moving goalposts without accounting for previous commitments. A new deadline does not erase an expired one.

WHEN DID DEADLINES STOP BEING DEADLINES IN BENUE?

By Aondoakaa Tersugh Daniel, 09/11/2026

Today, November 9, the 20-day ultimatum issued by the Group Managing Director of the Benue Investment and Property Company (BIPC), Dr. Raymond Asemakaha, for Golden Soya Oil from the rehabilitated Taraku Mills to reach the market has expired. The product is not on the shelves. A few days before the deadline, the GMD quietly told the public to expect a taste of it on December 5. What changed between the confident ultimatum and the new date? What stopped BIPC from keeping a deadline it set for itself? Benue people deserve an explanation, not another date.

The history of Taraku Mills makes this delay hard to excuse. We were told water and electricity were the obstacles. We then heard about rehabilitation, technical assessments, machinery readiness and the delivery of about 300 tonnes of soybeans. In October, Asemakaha announced that test production had started. Everything suggested a factory close to commercial operation.

So what is holding back the finished product? Did the test production expose technical faults? Is the problem refining, packaging, quality certification or power supply? Has the machinery developed new defects? Or was the 20-day timeline announced without any real assessment of the work left to be done? The GMD owes the public answers to these questions. He must also clarify what December 5 means. Is it the date Golden Soya Oil goes on sale in the market, or just another tasting ceremony? Benue people have seen enough factory milestones. They want products on the shelves.

Golden Soya Oil is not an isolated case. It points to a wider culture of project management under the Alia administration. Timelines are announced with great confidence, and many of them lapse without completion.

Take the Gboko township road project, valued at over ₦62 billion. When Governor Hyacinth Alia flagged off the roughly 55-kilometre reconstruction and dualisation in January 2026, a five-month completion period was announced. The aim was to finish before the election campaigns began. That deadline passed around June. How many kilometres are done today? Which sections remain? What is the revised completion date? The people of Gboko are entitled to answers. A project of this size cannot be run on occasional assurances and ceremonial inspections.

The Awajir–Oju road tells a similar story. It was awarded in September 2024, with work starting the following month, on a 12-month completion period for 52 kilometres. That placed the deadline around October 2025. By May 2025, the Bureau of Special Projects admitted that only about 25 per cent of the work was done and blamed insecurity and communal clashes. By August 2026, reports said about 19 kilometres had been asphalted and earthworks covered about 30 kilometres.

Nobody should dismiss the security challenges on that corridor. But naming a challenge is not the same as accounting for the work that remains. What is the revised programme? How much has been spent? What is outstanding, and when will the road be delivered? The same questions apply to the Makurdi and Gboko underpasses, which were due for commissioning on May 29, 2025. That date was missed because of additional drainage and technical problems.

The original 16 Makurdi township roads, flagged off in August 2023 with an 11-month completion period, also belong in this conversation. Their original deadline fell around July 2024. The administration has since declared them completed. Even so, their history shows why government must separate original commitments from revised timelines and actual delivery.

I am not denying that some projects have been completed, and I'm not claiming that every delay means abandonment. Our point is that public commitments must be documented, and performance must be measured against the dates and specifications first given to the people. Benue needs a transparent record of its capital projects, not selective announcements of whichever milestone is convenient at the moment.

This is the question the Alia administration must answer: when did deadlines stop being deadlines in Benue? Why should contractors and agencies announce completion dates if missing them carries no consequence? Why should government declare that a factory will start operating within a set period, then introduce a new date without explanation? Were these deadlines built on credible engineering assessments and realistic production schedules? Or were they simply convenient dates for generating public excitement?

A serious government knows the technical requirements of its projects before it announces timelines. When unforeseen problems arise, it says so promptly, explains the implications and publishes a revised programme. What is unacceptable is letting deadlines pass and presenting new dates as if the earlier commitments never existed.

I therefore call on Governor Hyacinth Alia to direct all relevant ministries, departments and agencies, including the Bureau of Special Projects, to publish a comprehensive status report on every major project whose original deadline has expired. For each project, the report should state the original completion date, the amount approved and released, the actual percentage of work done, the specific reasons for delay, the contractor responsible and a credible revised completion date.

BIPC should separately publish a detailed update on Taraku Mills. It should cover the outcome of the test production, the outstanding technical challenges, the current condition of the machinery and the actual date Golden Soya Oil will be commercially available. The administration must also tell the public what action it has taken against contractors who fail to honour their obligations. Accountability cannot be reduced to challenging critics to show the factories they have built before questioning government investments.

Benue people are not unreasonable. They understand that construction projects meet technical difficulties, that insecurity can disrupt work and that industrial production sometimes needs more time to reach acceptable standards. What they will not accept is a culture in which officials announce deadlines with confidence, miss them without explanation and return with new dates expecting applause.

A revised deadline does not erase an expired one. A new announcement does not settle an old commitment. A project inspection is not a substitute for project completion. Credibility is not built on the number of projects announced or the frequency of groundbreaking ceremonies. It is built by delivering what was promised, within the time promised, or by giving the people a credible explanation when that becomes impossible. Benue people deserve explanations, accountability and completed projects, not an endless calendar of promises.