VANDEIKYA SPECIALIST HOSPITAL: ACCOUNT FOR THE ₦8.86 BILLION
Why did the Benue Government record ₦8.86 billion as actual expenditure on upgrading Vandeikya General Hospital in 2024, only to announce in February 2025 that the Specialist Hospital had been approved and its contract would soon be awarded? Governor Alia must explain the contradiction, identify the contractors, account for the expenditure and show Benue people the hospital their money supposedly delivered.
By Aondoakaa Tersugh Daniel (Angom), 11/11/2026
Governor Hyacinth Alia has a question to answer, and it comes from his own government's books. The 2024 financial statements of the Benue State Government show ₦8,862,383,500 spent on upgrading the General Hospital in Zone A to a Specialist Hospital in Vandeikya. This is not an opposition allegation, a whistleblower's tale or a commentator's guess. The original allocation was ₦1 billion, it was revised to ₦8.9 billion, and actual expenditure stands at ₦8.862 billion. That is about 99.58 per cent of the revised figure, and a government that spends this close to its entire allocation must be able to show Benue people the hospital it paid for.
The trouble begins with what the government said afterwards. On February 11, 2025, Vanguard reported that the State Executive Council had approved the establishment of a Specialist Hospital in Vandeikya. The then Commissioner for Health and Human Services, Dr Yanmar Ortese, said the contract would soon be awarded. That announcement came more than a month after the close of the 2024 financial year, in which almost ₦8.9 billion had already been booked as spent on the same upgrade.
So what was being announced in February 2025? If it was a new project, why does the money for it appear to have been spent already? If it was a second phase, where is the line between the two? If the first spending had already delivered the hospital, why was a contract still waiting to be awarded? These questions will not go away with political explanations. The government must reconcile its accounts with its own announcements.
The classification of the money raises a further problem. The financial statements do not list the ₦8.862 billion as the construction of a new hospital. They place it under rehabilitation and repairs of hospital and health facilities, and the geographical breakdown assigns it to Vandeikya Local Government Area. We are entitled to ask what was rehabilitated or repaired at that price. Was the General Hospital extensively rebuilt? Were operating theatres, intensive care units, laboratories and diagnostic centres provided? Was specialist equipment bought and installed? How many beds were added, and how many doctors, nurses and technicians were deployed? A government that records nearly ₦9 billion in rehabilitation spending should be able to produce a full inventory of the work done.
The budget revision demands its own explanation. A ₦1 billion allocation became ₦8.9 billion, an increase of ₦7.9 billion or 790 per cent. A jump of that size needs a documented technical basis, proper budgetary authority and a matching expansion in scope. What changed between the original estimate and the revised one? Was there a fresh engineering assessment or a redesign? Who prepared the new cost estimate, and who approved it? Most importantly, who received the money, and was it paid under one major contract or several? The government should publish the contract awards, the identities of the contractors, the bills of quantities, the payment certificates and the project inspection reports. If the spending was proper and the work was done, those documents exist and the hospital can be seen.
Governor Alia cannot distance himself from spending recorded by his own administration. The project is also in his home local government, which makes public scrutiny even more natural. In August 2026, during the Thank You Tour of Jechira, his government had the perfect platform to showcase a healthcare investment of this size. Whether he mentioned it on that tour matters less than whether the government can show what the money delivered. The Commissioner for Health, the Accountant General, the Ministry of Finance and the procurement authorities should be able to give one consistent account of the project, from approval to payment to physical completion.
The governor must therefore answer plainly. Who won the contract for the Vandeikya Specialist Hospital upgrade, and when was it awarded? When did work begin, and how much has been paid to the contractor or contractors? What facilities did the ₦8.862 billion recorded as 2024 expenditure actually produce? Why did the government announce in February 2025 that a contract would soon be awarded when its records already showed almost the entire sum spent? If a separate phase exists, where are the documents? Above all, where is the hospital that accounts for this money, and what is its operational capacity today?
Benue people are not asking for another speech on the government's commitment to healthcare. They want an account of public money. A government cannot record ₦8.862 billion as spent, lift a project budget from ₦1 billion to ₦8.9 billion and expect citizens to accept the figures without proof of delivery. These are the government's own records, and the duty to reconcile them with the February 2025 announcement rests with the same government.
Governor Alia, show Benue the ₦8.86 billion Vandeikya Specialist Hospital. Let the people see what their money has delivered.